Lhyfe confirms initial objectives met for world’s first offshore H2 production project
Lhyfe, one of the world’s pioneers in the production of green and renewable hydrogen (H2), has announced that the operating results of its offshore H2 production pilot platform, Sealhyfe, which returned to dock in November 2023, confirm that the initial objectives have been met and enable another step forward for the company.
A world first for offshore H2 production. The Sealhyfe project, equipped with a 1-MW electrolyzer supplied by Plug, aimed to demonstrate that producing H2 offshore from renewable energy sources is already a reality. More specifically, the experiment aimed to:
Demonstrate Lhyfe’s ability to operate an industrial-scale production unit in an isolated environment
Prove the reliability of the electrolysis technology in harsh environmental conditions that are representative of the operating conditions of its future large-scale offshore sites
Provide a database of operating data that can be used to optimize and make production processes more reliable, and to test the technologies employed with a view to scaling them up to sites with ten times and then 100 times greater capacity.
A range of measurement and data collection instruments were installed onboard Sealhyfe to ensure precise management and control of all the production unit’s parameters from September 2022–November 2023, first at the quayside and then at sea.
A review of test results and analysis of equipment after 14 mos of trials indicated:
System responsiveness and versatility: As offshore H2 production is particularly relevant for providing services to the electricity grid, Lhyfe repeatedly tested the system’s versatility and responsiveness in a wide range of configurations. The experiment also confirmed the system’s ability to manage the variability of wind power in specific offshore conditions. The electrolysis system was operated as part of the planned research tests, including at maximum production capacity. The performance achieved was as high as on land, confirming the reliability of the installation.
Robustness: Throughout the trial, the production system equipment designed by Lhyfe was tested in extreme conditions for platform movement management, environmental stress, etc. In particular, Sealhyfe was confronted with five significant storms, including Ciaran, which swept along the Atlantic coast in October 2023, with waves > 10 meters (m) high and winds of > 150 kph. A complete analysis of the production system once it was back on land confirmed that all equipment had returned unharmed with its production capacity intact.
Equipment and system optimization: Throughout the experiment, onboard and remotely-controlled measuring instruments were used to identify ways of optimizing the efficiency and reliability of Lhyfe’s production units—including safety systems, electrical architecture, automation, fluid and stock management, etc.—for its other projects.
Remote control: The quayside benchmark testing phase helped to de-risk the project. The vast majority of impacts specific to offshore H2 production were identified and reduced. The site was then operated exclusively remotely from Lhyfe's control center, using supervision and control tools specifically developed by the company. The experiment made it possible to validate the software and algorithms for producing green and renewable H2, and to reduce the number of operations required in the marine environment. In total, Lhyfe carried out < 10 maintenance operations and the system was operated for 70% of the operating time.
Regulatory developments: As part of this world first, Lhyfe also worked with the French authorities to define the operating rules for a green H2 production unit operating within an urban, industrial and port environment, and also capable of operating in the open sea.
Overall, the Sealhyfe project enabled Lhyfe to develop its expertise in handling the constraints associated with offshore industrial deployment, thanks in particular to its experience integrating an isolated, offshore plant on a floating barge at sea.
Next steps: HOPE and the ramp-up onshore. The results of this experiment are already being incorporated into the HOPE project, which represents the second stage in Lhyfe’s offshore ambitions. This project, which Lhyfe presented with a consortium of nine partners, was selected by the European Commission for a €20-MM grant as part of the Clean Hydrogen Partnership, along with an additional €13-MM grant from the Belgian government. With HOPE, Lhyfe and its partners are changing scale and aiming to commercialize green H2 produced offshore. From 2026, this unprecedentedly large-scale project (10 MW) will be able to produce up to 4 metric tpd per day of green H2 at sea, which will be exported ashore by pipeline, and then compressed and delivered to customers.
The Sealhyfe project will also ensure that the production processes at Lhyfe’s land-based sites are reliable and optimized from the outset, so that they can be ramped up quickly and progressively. Lhyfe’s ambition is to have a production capacity of up to 22 metric tpd of green H2 by the end of 2024 and up to 80 metric tpd by 2026.
Matthieu Guesné, founder and CEO of Lhyfe, said, "The positive results of the Sealhyfe trial and the lessons we have learned from it represent a major new step for Lhyfe. We can now draw on our experience of three onshore sites and one offshore site to design our next green H2 production sites. This bolsters our expertise and the confidence of our partners, and supports the entire industry, because Sealhyfe has made offshore H2 production a reality."