Adani Energy Solutions Ltd. (AESL), India’s largest private transmission and distribution company and part of the globally diversified Adani portfolio, has won a power transmission project in Gujarat, which will supply green electrons for manufacturing green H2 and green ammonia in Mundra, Gujarat. The project which will cost $325,568, will be delivered to the nation in 36 months.
This project: transmission system for green H2/ammonia manufacturing potential in Mundra, Gujarat, involves upgrading the Navinal (Mundra) electrical substation by adding two large 765/400 kV transformers. Additionally, a 75 km long 765 kV double-circuit line will be constructed to connect this substation to the Bhuj substation.
The project will see the addition of 150 cKM of transmission lines and 3,000 MVA of transformation capacity to AESL’s overall transmission infrastructure, taking them to 25,928 cKM and 87,186 MVA, respectively.
AESL won the project under the tariff based competitive bidding (TBCB) mechanism and PFC Consulting Limited was the bid process coordinator. The project SPV was formally transferred to AESL on March 20, 2025.
This is AESL’s 6th order win this fiscal year, taking its orderbook to $6.6 MM.